Electrical installation

4.2 Checklist for electrical installation

4.2
Checklist for electrical installation
Use the following checklist to guide you through the electrical installation procedure for the
cabinet unit. Read the "Safety instructions" section at the start of these Operating
Instructions before you start working on the device.
Note
Checking the checklist
Check the boxes in the "Available" column appropriately if the associated task/option applies
to the cabinet unit. In the same way, check the "Completed" column once you have finished
the installation procedure to confirm that the activities are complete.