The foundation at the installation location must be horizontal and level, to ensure proper
functioning of the cabinet units.
● Care must be taken to ensure that the doors can be opened and closed and that the
locking systems work properly.
● Flat sections (such as doors, side panels and hoods) must be sealed correctly to ensure
compliance with the specified degree of protection.
● When cabinets are connected (e.g., transport units), air inlets caused by gaps must be
prevented.
Figure 3-1
The following points must be observed to ensure full functionality of the cabinet units:
● The foundation must be level and horizontal.
● Irregularities must be leveled out.
● Gaps where air can enter caused by leveling measures (e.g.:
sealed.
38
Requirements on the levelness of the floor
in the diagram) must be
Inverter cabinet units
Operating Instructions, 12/2014, A5E32923362A

Advertisement

Table of Contents
loading

Table of Contents