5.5

Procedure for commissioning via STARTER

Basic procedure using STARTER
STARTER uses a sequence of dialog screens for entering the required drive unit data.
Note
Default settings in dialog screens
These dialog screens contain default settings, which you may have to change according to
your application and configuration.
This is intentional!
Objective: By taking time to consider what configuration data you enter, you can prevent
inconsistencies between the project data and drive unit data (identifiable in online mode).
5.5.1

Creating the project

Click the STARTER symbol on the desktop to start the STARTER commissioning tool.
The first time you run the software, the main screen (shown below) appears with the
following windows:
● STARTER Getting Started Drive Commissioning
● STARTER project wizard
The commissioning steps are listed below as a numbered step sequence.
Inverter cabinet units
Operating Instructions, 12/2014, A5E32923362A
5.5 Procedure for commissioning via STARTER
Commissioning
145