Application manual
Measurement function application for a 380 kV OHL
Single line diagram for this application is given in figure 306:
380kV Busbar
800/5 A
380kV 120V
/
kV
3
3
P
Q
380kV OHL
ANSI09000039 V1 EN
Figure 306:
Single line diagram for 380 kV OHL application
In order to monitor, supervise and calibrate the active and reactive power as indicated
in figure
306
it is necessary to do the following:
1.
Set correctly CT and VT data and phase angle reference channel PhaseAngleRef
(see section
"Analog
2.
Connect, in PCM600, measurement function to three-phase CT and VT inputs
3.
Set under General settings parameters for the Measurement function:
general settings as shown in table 210.
level supervision of active power as shown in table 211.
calibration parameters as shown in table 212.
IED
ANSI09000039-1-en.vsd
inputs") using PCM600 for analog input channels
Section 3
IED application
755