procedure, see "3.7.15 Reflecting the XSCF network settings" in the Fujitsu
M10/SPARC M10 Systems System Operation and Administration Guide.
3.
Execute the poweroff command to stop the system.
XSCF>   poweroff -y  -a
4.
Remove the power cords of all the chassis from the input power.
5.
Connect the power cords to the PDU mounted in expansion rack 2.
For details, see
units of an expansion
6.
Connect expansion racks 1 and 2.
For details, see
7.
Fix expansion rack 2 in place.
For details, see
8.
Add a crossbar unit to the crossbar boxes (BB#80, BB#81) mounted in
expansion rack 1.
For details, see "Chapter 12 Maintaining the Crossbar Units" in the Crossbar Box
for Fujitsu M10/SPARC M10 Systems Service Manual.
9.
Mount the target SPARC M10-4S in the expansion rack.
For details, see
10. Reattach the labels of the crossbar cables, and replace the cables.
For details, see
expansion rack
11. Connect the crossbar cables and XSCF BB control cables to each chassis.
Crossbar cables (optical) and XSCF BB control cables are already laid in the
expansion rack. The work here is to connect the cables to each port of the
mounted chassis. Connect the cables according to the instructions written on the
labels.
For a cable connection diagram and a cable list, see
16BB Configuration (Connections through Crossbar
12. Connect the crossbar cables and XSCF BB control cables that pass between
the racks.
For details, see
XSCF
13. Set the ID of the SPARC M10-4S.
For details, see
14. Connect serial cables and LAN cables to a crossbar box.
For details, see
and
15. Connect the power cords to the SPARC M10-4S.
16. Connect the system management terminal to the crossbar box of the master
XSCF, and then perform an initial diagnosis of the system.
For details, see
Fujitsu M10/SPARC M10 Systems Installation Guide ・ July 2015
270
"3.3.1 Connecting the power cords to the power distribution
rack."
"3.3.3 Connecting
"3.3.2 Securing the
"3.4.2 Mounting the SPARC M10-4/SPARC M10-4S in a
"4.3.1 Changing crossbar cables (when subsequently installing
2)."
"4.3.2 Connecting crossbar
cables."
"4.1 Setting the ID (BB-ID) Identifying a
"5.2 Connecting Cables to the SPARC M10-4/SPARC
"5.4 Connecting Cables to a Crossbar
"Chapter 6 Performing an Initial System
racks."
rack."
"B.5 9BB Configuration to
Boxes)."
cables" and
"4.3.3 Connecting
Chassis."
Box."
Diagnosis."
rack."
M10-4S"