XSCF> poweron -y -a
24. Execute the showpparstatus command to check the operation status of the
physical partition.
In the following example, the [PPAR Status] field displays "Running," so the
physical partition is operating correctly.
XSCF> showpparstatus -p 0
PPAR-ID PPAR Status
00 Running
25. Execute the showboards command to check the system board (PSB) status.
In the following example, since both the [Conn] and [Conf] fields display "y" for
system board 02-0, the system board (PSB) has been added correctly.
XSCF> showboards -p 0
PSB PPAR-ID(LSB) Assignment Pwr Conn Conf Test Fault
---- ------------ ----------- ---- ---- ---- ------- --------
00-0 00(00) Assigned y y y Passed Normal
01-0 00(01) Assigned y y y Passed Normal
02-0 00(02) Assigned y y y Passed Normal
26. Reconfigure the logical domains.
Assign the resources of the installed SPARC M10-4S to an existing logical
domain or a newly configured logical domain. For details, see the Fujitsu
M10/SPARC M10 Systems Domain Configuration Guide.
9.3
Adding Expansion Rack 1 (Installation
for Expansion to Up to the 8BB
Configuration)
This section describes the installation procedure for expansion of direct connections
between chassis in a configuration of up to the 4BB configuration to connections
through crossbar boxes in a configuration of up to the 8BB configuration. This
procedure corresponds to pattern B (1) in
9.3.1
Changing a multiple-BB configuration into 1BB
configurations and releasing their connections
Remove the SPARC M10-4S from the existing multiple-BB configuration (direct
connections between chassis), change it to 1BB configurations, and release their
Figure
Chapter 9 Installing a System with a Building Block Configuration
8-1.
265