25) Inspection of Tilt Cylinder and
Reserve Tank
1.
Check reservoir 1 and upper oil seal for dameges and
wear. Replace reserve tank if necessary.
2.
Check tilt rod 2 for bend, any scratched of sliding surface
and wear. Replace tilt rod if necessary.
3.
Check tilt rod for bend and hard rusting. If lightly rusting,
finish by using sand paper #400 - #600, and or replace tilt
rod if necessary.
26) Installation of Tiller Handle
1.
Install new o-ring 1 to PTT unit 1.
2.
Install reservoir 3 to PTT unit and tighten bolts 4 to
specified torque.
Resreve Tank Bolt 4 :
4.5 N · m (3.3 lb · ft) [0.45 kgf · m]
3.
Use vise to fix PTT unit 1 that is protected at both sides
with wood pieces or aluminum plates a.
4.
Secure tilt rod 6 and tighten joint metal (rod eye) 5 by
using wrench.
Joint Metal 5 :
4.5 N · m (3.3 lb · ft) [0.45 kgf · m]
TLD D30/40/50B2 2013
2
4
1
1
a
a
5
6
1
3
2
7
7-45