Installing The Ftir Analyzer Into The Rack; Figure 2-1. Removing The Shipping Screws - Thermo Scientific Omni FTIR Multi Gas CEMS Instruction Manual

Table of Contents

Advertisement

Installing the
FTIR Analyzer
into the Rack
Thermo Fisher Scientific
analyzer to remove the shipping restraint before the analyzer is installed in
the rack.
Figure 2–1. Removing the shipping Screws
Remove the left access panel and set aside. The panel will remain connected
to the FTIR by wiring for the cooling fan. Remove the interferometer
shipping restraint. The shipping restraint is a single piece of foam wedged
into the slot. Be careful to not allow foam fragments to fall into the
interferometer assembly. Retain the shipping restraint for future use.
Replace the side panel.
Lift the analyzer from the pallet. The analyzer weighs about 130 lbs. (60
kg), so at least two people will be needed to lift it.
CAUTION To prevent damage to the interferometer; do not apply electric
power to the analyzer before internal shipping restraints have been
removed.
CAUTION Lift from each side of the analyzer, not from the front and back.
Damage to the unit may occur.
Position the analyzer on the rack slide per
System Installation, Start Up and Shut Down

Installing the FTIR Analyzer into the Rack

Figure
2–2.
Omni FTIR Multi Gas CEMS Instruction Manual
2-3

Advertisement

Table of Contents
loading

This manual is also suitable for:

108004-00

Table of Contents