Preparing for Installation

3-4-1

Verify Customer Order

Compare items received by the customer to that which is listed on the delivery order. Report any items
that are missing, back ordered or damaged.
3-4-2

Physical Inspection

3-4-2-1

System Voltage Settings

Verify that the scanner is set to the correct voltage. The Voltage ratings for the LOGIQ P3 Scanner
is found on Rating label near the Circuit Breaker at the rear of the system
WARNING
WARNING
Connecting a LOGIQ P3 scanner to the wrong voltage level will most likely destroy the
scanner.
3-4-3

EMI Protection

This Unit has been designed to minimize the effects of Electro Magnetic Interference (EMI). Many of the
covers, shields, and screws are provided primarily to protect the system from image artifacts caused by
this interference. For this reason, it is imperative that all covers and hardware are installed and secured
before the unit is put into operation.
3-4-4

Checking the Components

When a new system arrives, check that none of the components are damaged or in short supply. If
shipping damage or shortage occurs, contact the address shown in Chapter 1.
If the Power Plug is Modified or replaced to Suit the local Conditions and regulations, Ground
CAUTION
continuity check should be performed between Ground Pin on the Plug and the Metal Part on
C
the LOGIQ P3. Refer Section 10-7 for more details.
PROPRIETARY TO GE
8
EVISION
Chapter 3 Installation
LOGIQ P3 S
M
ERVICE
ANUAL
3-9

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Logiq p3 bt10Logiq p3Logiq p3 expertLogiq p3 vet

Table of Contents