3.18.2
Checklists for commissioning
Checklists for commissioning 1FW6 built-in torque motors
Please thoroughly familiarize yourself with the safety instructions and observe the checklists
below before starting any work.
Table 3- 21
Checklist (1) - general checks
Check
Are all of the necessary components of the configured drive line-up available, correctly dimensioned,
correctly installed and connected?
Are the manufacturer's documentation for the system components (e.g. drive system, encoder, cooling
system, brake) and the "SIMOTICS T-1FW6 built-in torque motors" Configuration Manual available?
Are the following up-to-date SINAMICS documents available?
SINAMICS S120 Commissioning Manual
•
SINAMICS S120 Getting Started
•
SINAMICS S120 Function Manual Drive Functions
•
SINAMICS S120/S150 List Manual
•
Was the Chapter "Checklists for commissioning SINAMICS S" taken into account?
Is the motor type to be commissioned known?
(e.g. 1FW6 _ _ _ – _ _ _ _ _ – _ _ _ _)
As a minimum, is the following data for the motor known, if it involves a "third-party motor"?
(A "third-party motor" is every motor that is not saved as standard in the Siemens commissioning soft-
ware.)
Rated motor current
•
Rated motor speed
•
Motor pole pair number
•
Motor torque constant
•
Maximum motor speed
•
Maximum motor current
•
Motor limit current
•
Motor moment of inertia
•
Motor stator resistance, cold
•
Motor stator leakage inductance
•
Are the environmental conditions in accordance with "SIMOTICS T-1FW6 built-in torque motors" Operat-
ing Instructions in the permitted range?
Is it guaranteed that the maximum permitted temperature of the rotors does not exceed 120° C?
Is it guaranteed that at least two people work together?
STARTER Commissioning Manual
Commissioning Manual, (IH1), 07/2016, 6SL3097-4AF00-0BP5
3.18 Commissioning SIMOTICS T-1FW6 built-in torque motors
Commissioning
OK
237