Commissioning
3.5 Commissioning the servo control booksize format for the first time
What?
3.1
Inserting
an infeed unit
3.2
Infeed
3.3
Infeed - additional
data
3.4
Process data
exchange
(infeed)
3.6
Configuration,
summary
NOTICE
Damage to the infeed for control using another Control Unit
If the infeed is controlled by a Control Unit other than that used for the Motor Module, the
"Ready" signal for the infeed r0863.0 must be interconnected with drive parameter p0864
"Infeed ready" via a digital input/output. If this is not taken into account, the infeed may be
damaged.
128
How?
If there is no DRIVE-CLiQ connection to the Control Unit, then
you must manually enter the data of the infeed unit using the
wizard.
1. Double-click in the project tree on "Infeeds".
2. Double-click "Insert infeeds".
3. Enter a name for the infeed.
4. Select the type.
5. Click "OK".
1. Enter a component name.
2. Select the line voltage range.
3. Select the cooling type.
4. Select the baud rate.
5. The available components are now in the selection list.
6. Select the required infeed from the list.
7. Click "Continue >".
1. Activate the line/DC-link identification when switching-on for
the first time.
2. Accept the device supply voltage from the previous window.
The rated line frequency is determined automatically.
3. Make sure that the option "Line filter available" is activated.
4. For an infeed in the "booksize" format, select a line filter.
You can select one from several versions.
5. If applicable, enter the number of parallel infeeds.
6. Where relevant, select a Voltage Sensing Module.
7. Where relevant, select an external Braking Module.
8. Where relevant, select master/slave operation for several
infeeds.
9. Click "Continue >".
One of three telegrams can be selected for communication: 370,
371 and 999.
1. Select the required telegram (e.g. 370).
2. Click "Continue >".
Configuration of the infeed unit has been completed. A summary
is displayed.
1. Click "Complete".
STARTER Commissioning Manual
Commissioning Manual, (IH1), 07/2016, 6SL3097-4AF00-0BP5
Comment
If the line environment or
DC-link components are
changed, line/DC-link iden-
tification should be repeat-
ed.
-
-
-
The infeed unit data can be
copied to the clipboard for
plant documentation pur-
poses and then added to a
text program, for example.