Site Preparation Checklist (Not-Racked Systems); Table 14: Site Preparation Checklist - Oracle FS1-2 Installation Manual

Flash storage system (not racked)
Hide thumbs Also See for FS1-2:
Table of Contents

Advertisement

Table 13: High voltage three-phase PDU for Oracle Flash Storage Systems
(continued)
High Voltage
Maximum input current for each cord
Outlet receptacles (number/type)
Outlet groups for each PDU
PDU power cord length

Site Preparation Checklist (Not-racked Systems)

Before system installation, complete the tasks outlined in the pre-installation
checklist as part of the site preparation and installation planning. Your Oracle
Sales team can arrange for site audit and installation services.

Table 14: Site preparation checklist

Check
Pre-installation site preparation: Prior to system delivery, a site audit must be
conducted.
Site preparation or pre-installation planning items
Determine the suitability of access routes to the installation location, such
as carpet, doors, elevators, floor strengths, and ramps.
Determine the load capacity of the floor where the system is to be
installed.
Verify the cleanliness of the site and inform the customer to perform any
required cleaning.
Note any problems or peculiarities at the site that require special
equipment.
Determine if there will be raised floors, where the cabling will be under
the floor. For raised floors, cutout tiles with protected edges will be needed
prior to installation.
Oracle FS Systems: Installation Overview
3Ph (5W + ground)
25A
42/C13 (seven for each outlet group)
6/C19 (one for each outlet group)
6
2 meters (6.6 feet)
PDU power cords are 4 meters (13 feet)
long, but sections are connected for internal
routing in the rack.
28