5. Pull out the clip from the bracket and remove the shift cable
and select cable.
6. Installation is reverse order of the removal.
Inspection Procedure
1. The shift lever should be positioned in neutral.
2. Apply liquid gasket on the cable contact surface.
3. Keep 130 mm between the center of the cable end-eye
and floor.
Standard
Notice
If necessary, adjust the adjust nut.
130 mm
MANUAL TRANSMISSION 5B-13