Initial Start-up
7.2 Initial Start-up
7.2.1
Switching on of
KEB COMBIVERT
©
KEB Antriebstechnik, 2002
All Rights reserved
After all preparatory measures have been carried out the KEB COMBIVERT F5 can
be switched on.
The sequence of the switch-on procedure as shown below refers to supplied units
with factory setting. Because of the multitude of programs we cannot take into
consideration customer-specific adjustments.
Picture 7.2.1
Swtich on of KEB COMBIVERT
Switch on inverter
Switch control release
Display dark ?
Is an
error message
displayed ?
(E.xx)
Display „noP" ?
Yes
Press „FUNCT"-key
Display „CP.1"
check the default
configuration
Name: Basis
KEB COMBIVERT F5-G / B
Start-up
1. Check mains voltage
2. Operator inserted
correctly?
Yes
3. Check connection of
control card for short
circuit
Look up cause and remedy in
Yes
chapter 9 „Error Assistance"
Date
Chapter
01.02.02
Section
Page
7
2
3
7
Need help?
Do you have a question about the COMBIVERT F5 BASIC and is the answer not in the manual?
Questions and answers