IDS2000 Dual-Row Aisle Containment
Installation Guide (Split-type Skylight, Old-Version
Sliding Door)
No.
4
5
6
3.4.1 Installing a Sliding Door
Context
Figure 3-23
Figure 3-23 Structure
Issue 02 (2015-06-30)
Check Item
vertical distances are 2200 mm
(tolerance: ± 3 mm).
If a support is used, the vertical
distance must also be 2000 mm or
2200 mm between the cabinet top and
the upper surface of the ESD floor.
The optimal deviation of vertical
distances is 0 mm between the upper
surface of the ESD floor and the upper
surface of the support. A maximum of
3 mm is acceptable.
After leveling cabinets, measure the
height from the ESD floor.
shows the structure of a sliding door.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3 Installation Scenarios in Dual Row Aisle Containment
Result
NA
NA
NA
47