Huawei IDS2000 Dual-Row Aisle Containment Installation Manual page 7

Split-type skylight, old-version sliding door
Hide thumbs Also See for IDS2000 Dual-Row Aisle Containment:
Table of Contents

Advertisement

IDS2000 Dual-Row Aisle Containment
Installation Guide (Split-type Skylight, Old-Version
Sliding Door)
10.1 Cable Routing for the Dual-row Aisle Containment Scenario ................................................................................ 149
10.2 Installation Positions and Cable Routing for Monitoring Components .................................................................. 152
10.4 Cable Routing for the Cabinet Lighting .................................................................................................................. 158
10.5 Cable Routing for the Aisle Lighting System ......................................................................................................... 159
10.6 Cable Routing for Skylight Magnetic Locks .......................................................................................................... 162
10.7 Routing Power Cables ............................................................................................................................................ 163
10.8 Grounding Cabinets ................................................................................................................................................ 165
10.9 Routing Signal Cables ............................................................................................................................................ 166
10.10 Installing Cables for the Power Supply and Distribution System ......................................................................... 167
10.10.1 Connecting Cables to Battery Cabinets ............................................................................................................. 167
10.10.2 Connecting Cables to the Power Supply and Distribution System .................................................................... 190
10.11 Connecting Cables to the Temperature Control System ........................................................................................ 191
10.12 Connecting Cables to the Data Center Management System ................................................................................ 192
10.12.1 Preparing a Monitoring Cable ............................................................................................................................ 192
10.12.2 Port Description for the CCU Collector ............................................................................................................. 195
10.12.3 Port Description for the ECC Collector ............................................................................................................. 202
10.12.4 Connecting a Monitoring Cable to a CCU Collector ......................................................................................... 204
10.12.5 Connecting a Monitoring Cable to the ECC Collector ...................................................................................... 205
10.12.6 Connecting a Monitoring Cable to a LAN Switch ............................................................................................. 206
10.12.7 Connecting a Monitoring Cable to an RH2288.................................................................................................. 207
10.12.8 Cable Connection for the NetEco ...................................................................................................................... 207
10.12.9 Connecting Monitoring Cables to a WCON-22Z Skylight Controller ............................................................... 208
10.12.11 Connecting a Monitoring Cable to a Camera ................................................................................................... 214
10.12.12 Connecting a Monitoring Cable to a Door Status Sensor ................................................................................ 215
10.12.16 Connecting a Cable to the WLDS900 Water Sensor ........................................................................................ 219
10.12.17 Connecting Cables to the SJ535A Water Sensor .............................................................................................. 220
10.12.18 Connecting a Monitoring Cable to a Point Water Sensor ................................................................................ 222
10.12.19 Connecting a Monitoring Cable to a Hydrogen Sensor ................................................................................... 223
10.12.21 Connecting a Monitoring Cable to the MS899 Electronic Door Lock ............................................................. 225
10.12.22 Installing the SMS Modem .............................................................................................................................. 227
10.12.23 Connecting Monitoring Cables to a Lighting Control Box .............................................................................. 228
10.12.24 (Optional) Connecting a Monitoring Cable to an NVR ................................................................................... 229
10.12.25 Connecting a Monitoring Cable to an ACRD502 Air Conditioner .................................................................. 230
10.12.26 Connecting a Monitoring Cable to a PEX Air Conditioner ............................................................................. 231
10.12.27 Connecting a Monitoring Cable to a CRV Air Conditioner ............................................................................. 233
Issue 02 (2015-06-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Contents
vi

Advertisement

Table of Contents
loading

Table of Contents