3.
Keep the gaps between skylight and skylight connective plates at 3± 1 mm.
Step 4 Secure the magnetic lock to its fastener using an M6 screw, as shown in
Figure 3-10 Installing a magnetic lock
Step 5 Install control skylights, as shown in
1.
2.
Issue 02 (2015-06-30)
Figure 3-9 Securing adjacent skylight connective plates
Install the other skylight connective plates in sequence using the same method.
Install the monitoring components, and connect the cables to the ports. For details about
the installation of the monitoring components, see
Monitoring
Components.
Lift the control skylight (with the monitoring components installed) to the top of the aisle,
and face the rubber plug of the cable hole away from the aisle, as shown in
Secure the skylight to the skylight connective plates using M4 screws, as shown in
Figure
3-11.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3 Installation Scenarios in Dual Row Aisle Containment
Figure
3-13.
9.1.6 Installing and Connecting
Figure
3-10.
Figure
3-11.
38

Advertisement

Table of Contents
loading

Table of Contents