(MAP05A1, MAB05B1) V100R002C00 User Manual Issue Date 2021-12-30 HUAWEI DIGITAL POWER TECHNOLOGIES CO., LTD.
Page 2
Notice The purchased products, services and features are stipulated by the contract made between Huawei Digital Power Technologies Co., Ltd. and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
User Manual 1 About This Document About This Document Purpose This document describes the iSitePower-M system (including the power module MAP05A1 and battery module MAB05B1) in terms of its overview, installation, commissioning, maintenance, and technical specifications. Intended Audience This document is intended for: ●...
Product Description 3.1 Overview The iSitePower-M is a small-sized fuel-free hybrid power solution. It integrates photovoltaics (PV), grid, and batteries into one and supports the access and scheduling of solar energy, generator set (genset), grid power, and batteries. It is...
(MAP05A1, MAB05B1) User Manual 5 Application Scenarios Application Scenarios The iSitePower-M is mainly used in houses, apartments, shops, and business outlets. Based on different energy inputs, the application scenarios are classified into six types. ● Solar-only scenario ● Grid scenario ●...
If there is no PV input, hold down the manual ON/OFF switch for 5s. Step 2 Switch on the upstream AC input circuit breaker for the iSitePower-M system. Step 3 After the initial installation and power-on, observe the LED indicator to check the running status.
The app cannot be installed on a tablet, folding screen, or landscape screen device. Downloading and Installing the NetEco App ● Method 1: Search for NetEco in Huawei AppGallery and download the latest installation package. ● Method 2: Scan the QR code to download and install the latest installation package.
Powering Off the System Step 1 Switch off the upstream AC input circuit breaker for the iSitePower-M system. Step 2 Set the DC SWITCH on the power module to OFF. Step 3 Hold down the manual ON/OFF switch for 5s to shut down the battery module.
Page 95
Installing Modules and Cables for Battery Recharge WARNING Use standard cables provided by Huawei to connect power modules and battery modules. Do not use non-standard cables (such as extension cables and interconnection cables). If BAT+ and BAT– cables are reversely connected, the device will be damaged.
Page 96
Step 4 After the charge is complete, turn off the upstream AC input circuit breaker of the iSitePower-M system and then the DC SWITCH. Hold down the manual ON/OFF switch for 5s to shut down the battery module. If other batteries need to be charged, repeat the preceding steps.
NMS and the mobile app may fail. Before connecting the iSitePower-M to the NMS through a home WiFi router, check the LAN IP address of the router. The IP address cannot be 192.168.0.X, 192.168.7.X, or 192.168.198.X.