Commissioning

5.1

Commissioning guidelines

Overview
Converter with the CU250S-2 Control Units
Operating Instructions, 04/2018, FW V4.7 SP10, A5E31759476B AG
1. Define the requirements to be met
by the drive for your application.
(Page 127)
2. Restore the factory settings of the
inverter if necessary.
(Page 152)
3. Check if the factory setting of the
inverter is sufficient for your
application.
(Page 130)
4. Set the following for quick
commissioning of the drive:
– The closed-loop motor control
– The inputs and outputs
– The fieldbus interface
(Page 134)
5. Check if additional inverter
functions are required for the
application.
(Page 157)
6. If necessary, adapt the drive.
(Page 157)
7. Save your settings.
(Page 361)