Who may perform the acceptance test of the inverter?
Personnel from the machine manufacturer, who, on account of their technical qualifications
and knowledge of the safety functions, are in a position to perform the acceptance test in the
correct manner are authorized to perform the acceptance testing of the inverter.
Wizard for the acceptance test
The "Startdrive Advanced" commissioning tool (requires an appropriate license) includes a
wizard for the acceptance test of the safety functions integrated in the drive.
"Startdrive Advanced" guides you through the acceptance test, generates the appropriate
traces to analyze the machine response – and generates an acceptance report as Excel file.
Further information is provided on the Internet:
ww/en/view/109752254)
Reduced acceptance test after function expansions
A full acceptance test is necessary only after first commissioning. A reduced acceptance test
is sufficient when safety functions are expanded.
Measure
Functional expansion of the ma‐
chine (additional drive).
Transfer of inverter settings to oth‐
er identical machines by means of
series commissioning.
Converter with the CU250S-2 Control Units
Operating Instructions, 04/2018, FW V4.7 SP10, A5E31759476B AG
Startdrive, system requirements and download
6.17 Safe Torque Off (STO) safety function
(https://support.industry.siemens.com/cs/
Acceptance test
Acceptance test
Documentation
Yes.
● Supplement machine overview
Only check the safety
● Supplement inverter data
functions of the new
● Add function table
drive.
● Log the new checksums
● Countersignature
No.
● Add machine description
Only check the control
● Check checksums
of all of the safety func‐
● Check firmware versions
tions.
Advanced commissioning
257