Install the Rack Rails for the Controller
Prior to adding Controllers, install rails into the rack for each Controller that you
plan to add.
Prerequisites:
•
•
•
•
1
Mark the rack mount hole where you plan to mount the Controller.
The Controller requires two standard rack units (2U) of vertical space.
2
Remove the rails from the packaging.
3
Position the front of the left rail behind the left front rack rail.
Figure 12: Controller rack mount location
Ensure that you have adequate room to work around the rack while
installing the rails and the Controller.
Attach an electrostatic discharge (ESD) wrist strap to your wrist, and stand
on an ESD mat while replacing components.
Ensure that you have a Phillips Number 2 screwdriver with at least a 4-inch
shaft.
If you are installing the rails in a rack with threaded holes, make sure you
have a Torx Number 20 screwdriver.
Oracle FS1–2 Global Procedures
46