How to Program

2.1.7 Initial Commissioning

2
2
The easiest way of carrying out the initial commissioning is by pressing [Quick Menu] and following the quick set-up
procedure using LCP 102 (read Table 2.3 from left to right). The example applies to open-loop applications.
Press
Quick
Menu
Parameter 0-01 Language
Parameter 1-20 Motor Power [kW]
Parameter 1-22 Motor Voltage
Parameter 1-23 Motor Frequency
Parameter 1-24 Motor Current
Parameter 1-25 Motor Nominal Speed
Parameter 5-12 Terminal 27 Digital
Input
Parameter 1-29 Automatic Motor
Adaptation (AMA)
Parameter 3-02 Minimum Reference
Parameter 3-03 Maximum Reference
Parameter 3-41 Ramp 1 Ramp Up Time
Parameter 3-42 Ramp 1 Ramp Down
Time
Parameter 3-13 Reference Site
Table 2.3 Quick Set-up Procedure
18
®
VLT
AutomationDrive FC 301/302
Q2 Quick Menu.
OK
Set language.
OK
Set motor nameplate power.
OK
Set nameplate voltage.
Set nameplate frequency.
OK
Set nameplate current.
OK
Set nameplate speed in RPM.
OK
If terminal default is [2] Coast
inverse, it is possible to change
OK
this setting to [0] No function.
No connection to terminal 27 is
then needed for running AMA.
Set desired AMA function.
OK
Enable complete AMA is
recommended.
Set the minimum speed of the
OK
motor shaft.
Set the maximum speed of the
OK
motor shaft.
Set the ramp-up time with
reference to synchronous motor
OK
speed, n
.
s
Set the ramp-down time with
OK
reference to synchronous motor
speed, n
.
s
Set the site from where the
OK
reference must work.
Danfoss A/S © 10/2018 All rights reserved.
OK
MG33MP02

Advertisement

Table of Contents
loading

This manual is also suitable for:

Vlt automationdrive fc 301

Table of Contents