37. Cut two 6.1 m (20 ft) deployment wires from a 0.8
mm (18 gage) or thicker multi-strand wire. These
wires will be used to fabricate the passenger
deployment harness.
38. Strip 13 mm (0.5 in) of insulation from both ends of
the wires.
39. Twist together one end from each of the wires in
order to short the wires.
40. Twist together the 2 connector wire leads from the
high circuits from both stages of the I/P module to
one set of deployment wires. Refer to "SIR
Connector End Views" in order to determine the
correct circuits.
41. Inspect that the 3-wire connection is secure.
42. Bend flat the twisted connection.
43. Secure and insulate the 3-wire connection to the
deployment harness using electrical tape.