Oil Pump Outlet Tube Assembly-Renew; Oil Thermostat Cooler Pipe Assembly-Renew; Oil Temperature Controller-Renew - Aston Martin V8 Vantage Workshop Manual

Table of Contents

Advertisement

Cooling System (03.03)
Engine (03.00)
6. Remove bolts securing oil pipes to block.
7. Release both pipes from block and remove inlet pipe.
Installation
1. Renew o-ring on remaining oil pipe.
2. Install inlet pipe and position both pipes into block.
3. Install bolts securing oil pipes to block (torque).
4. Install LH exhaust manifold.(see Workshop Manual
procedure XREF: 419 Gasket - Exhaust Manifold - LH -
Renew
5. Install bolt, pipes to bracket.
6. Install harness clip to pipe.
7. Install P.A.S pump. (see Workshop Manual
procedure03.05.AAXREF: 404 Pump - Power Steering -
Renew
8. Fill tank with approximately amount of displaced oil and
replace cap.
9. Use handbook procedure to check oil level.

Oil Pump Outlet Tube Assembly-Renew

Repair Operation Time (ROT)
Item
Oil Pump Outlet Tube Assembly-Renew
Removal
1. Remove P .A.S pump (see Workshop Manual procedure
03.05.AA Pump - Power Steering - Renew).
2. Remove pipe from oil controller (position container to
catch oil).
3. Remove bolt, pipes to bracket.
4. Remove LH exhaust manifold (see Workshop Manual
procedure 09.00.CD Gasket - Exhaust Manifold - LH -
Renew).
5. Remove harness to pipe clip.
6. Remove bolts securing oil pipes to block.
7. Release both pipes from block and remove outlet pipe.
Installation
1. Renew o-ring on remaining oil pipe.
2. Install outlet pipe and position both pipes into block.
3. Install bolts securing oil pipes to block (torque).
4. Install bolt, pipes to bracket.
5. Install harness clip to pipe.
6. Install LH exhaust manifold (see Workshop Manual
procedure 09.00.CD Gasket - Exhaust Manifold - LH -
Renew).
7. Install P.A.S pump (see Workshop Manual procedure
03.05.AA Pump - Power Steering - Renew).
8. Fill tank with approximately amount of displaced oil and
replace cap.
9. Use handbook procedure to check oil level.
3-4-6
Oil Thermostat Cooler Pipe Assembly-
Renew
Repair Operation Time (ROT)
Item
Oil Thermostat Cooler Pipe Assembly-
Renew
Removal
1. Raise vehicle on ramp.
2. Remove undertray (see Workshop Manual procedure
01.02.NB Undertray - Front - Renew).
3. Remove LH air filter box (see Workshop Manual
procedure 03.12.AB Air Filter Box LH Renew).
4. Remove pipe from oil thermostat (position container to
catch oil).
5. Unclip pipe (x4) from inner wing.
6. Remove pipe from oil cooler and pull out from inner
wing (position container to catch oil).
Installation
1. Install pipe to oil cooler (torque) through inner wing.
Code
2. Clip pipe (x4) to inner wing.
03.02.CF
3. Install pipe to oil thermostat and ensure correct
alignment in oil tank bracket.
4. Install undertray (see Workshop Manual procedure
01.02.NB Undertray - Front - Renew).
5. Lower vehicle on ramp.
6. Install LH air filter box (see Workshop Manual
procedure 03.12.AB Air Filter Box LH Renew).
7. Fill tank with approximately amount of displaced oil and
replace cap.
8. Use handbook procedure to check oil level.

Oil Temperature Controller-Renew

Repair Operation Time (ROT)
Item
Oil Temperature Controller-Renew
Removal
1. Raise vehicle on ramp.
2. Remove undertray (see Workshop Manual procedure
01.02.NB Undertray - Front - Renew).
3. Remove pipes from oil thermostat (position container to
catch oil).
4. Remove controller from body (bolts x2).
Installation
1. Install controller to body (bolts x2) (torque).
2. Install pipes to oil thermostat (torque) ensure correct
alignment in oil tank bracket.
3. Install undertray (see Workshop Manual procedure
01.02.NB Undertray - Front - Renew).
4. Fill tank with approximately amount of displaced oil and
replace cap.
5. Use handbook procedure to check oil level.
Workshop Manual