Pre-Upgrade Tasks — If the Target S8300 is the
Primary Controller
If the S8300 is configured as an LSP, skip to
CAUTION:
If you are upgrading an S8300 primary controller that has LSPs registered to it, the LSPs
must be upgraded before the primary controller. (You can use the SAT command, list
media-gateway, to see if there are LSPs registered to the S8300.)
Perform the following procedures if you are upgrading an S8300 that is configured as a primary
controller.
NOTE:
It is no longer necessary to disable Terminal Translation Initialization (TTI) before an
upgrade or to enable it after an upgrade.

Clear Alarms

1
On the Maintenance Web Interface under Alarms and Notification (Alarms for R2.0), click
Current Alarms
2
If no alarms are listed, skip the next two steps.
3
If alarms are listed, click
4
Resolve any remaining major alarms through the Communication Manager SAT.

Check Link Status

1
Open a SAT session.
2
Enter
display communication-interface links
3
Note all administered links.
4
Enter
status link number
5
Enter
list signaling group
6
Note the signaling groups listed by number.
7
For each of the signaling groups listed, enter
8
Make a note of any links that are down.

Record All Busyouts

1
At the SAT prompt, type display errors and press
2
Look for type 18 errors and record any trunks that are busied out — you will return them to their
busy-out state after the upgrade.
Installation and Upgrades for G700 and S8300
December 2003
Upgrading an Existing G700 with an S8300 — R2.0 to R2.x
Upgrade the S8300
(Current Alarms for R2.0).
.
Clear All
for each administered link.
.
On-site Preparation for the Upgrade