Enable Announcements, If Necessary
1
Only if specifically requested by the customer or your planning documents, at the SAT prompt,
type
enable announcement-board <gateway_number> V9,
number of the G700 Media Gateway you just added and
means Media Gateway number 2, slot V9.
2
Press
E NT ER
The system displays the message Command successfully completed.
Save Communication Manager Translations
Save translations again after all Communication Manager administration is complete.
— At the SAT prompt, type

Complete the Installation Process

Consult the planning documentation to obtain the necessary information to complete the installation. Part
of the final process will be to:
Connect and administer test endpoints.
Test the endpoints.
Complete the electrical installation
Enable adjunct systems
This completes the upgrade procedures.
Installation and Upgrades for G700 and S8300
December 2003
to enable announcements.
save translation
Installing a New G700 without an S8300
Complete the Installation Process
where <gateway_number> is the
is the virtual slot (for example,
V9
.
4
2V9
209

Advertisement

Table of Contents
loading

This manual is also suitable for:

S8300

Table of Contents