Preparing for installation
Table 4-1. DocuPrint NPS/IPS installation planning checklist (Continued)
Week
Activity
-3
•
Schedule hardware delivery.
•
Prepare the site:
–
Provide a table with adequate
space for hardware and
cables.
–
Ensure and install proper
electrical receptacles.
–
Obtain and string bus and tag
cables (must be fully
populated), if needed.
–
Install network to system
location.
–
Install Token Ring to system
location (if appropriate).
–
Install Ethernet to system
location (if appropriate).
–
Establish network addresses
and logical unit names for print
server and user workstations.
–
Complete preinstallation
checklist.
–
Provide table with adequate
space for hardware and
cables.
–
Ensure and install proper
electrical receptacles.
–
Ensure proper operating
environment.
–
Generate the host for an AFP1
device and IPL, as required.
–
Provide analog phone line
access for optional Sixth
Sense installation.
4-6
Reference
Responsibility
Sales rep
Customer and
Chapters 4 to 6
Xerox
Customer
Installation Planning Guide
Date
completed
_________
_________
_________
_________
_________
_________
_________
_________
_________
_________
_________
_________
_________
_________