Installing a NetIron XMR 8000 router

1
4. Connect the -48V cable to the negative terminal on the power supply and the 0V cable to the
5. Replace the transparent cover.
This equipment installation must meet NEC/CEC code requirements. Consult local authorities for
regulations.

Final steps

Follow these steps in the order listed to complete the installation:
Installing a NetIron XMR 8000 router
The following sections describe how to install a NetIron XMR 8000 router.

Preparing the installation site

Before installing the router, plan the location and orientation relative to other devices and
equipment. For cooling purposes, allow a minimum of six inches of space between the sides, front,
and the back of the router and walls or other obstructions. If a router is installed in a perforated
enclosure, the perforations must cover at least 60 percent of the surface.
Ensure that the proper power and network cabling is installed in the site. For information on
cabling, refer to
a management station"

Unpacking a NetIron XMR 8000 router

The NetIron XMR 8000 router ships with the following items:
150
#8 AWG power supply wire
positive terminal on your DC power source.
NOTE
DC return must be isolated from the device ground (DC-I) when connecting to the power supply.
"Attaching a management station"
"Activating the power source"
"Verifying proper operation"
"Installing NetIron XMR 8000 router power supplies"
on page 193.
Router chassis with the appropriate number of switch fabric modules already installed in the
slot marked SF and a slot blank installed in all other module slots.
1
Brocade MLX Series and NetIron XMR Hardware Installation Guide
on page 156, and
"Attaching
53-1003821-01

Advertisement

Table of Contents
loading

Table of Contents