CAUTION
To ensure adequate bonding when attaching the ground lug, a minimum of 20 PSI of torque is
required to be applied to the mounting hardware used to attach the ground lug.
FIGURE 59
1
4. Connect the -48V cable to the negative terminal and the 0V cable to the positive terminal on
5. Replace the transparent cover.
This equipment installation must meet NEC/CEC code requirements. Consult local authorities for
regulations.
Final steps
Complete these steps in the order listed:
•
•
•
Installing a Brocade MLX-32 router
The Brocade MLX-32 router can be installed on a 2-post Telco open frame rack or a 4-post
enclosed rack or cabinet.
Preparing the installation site
Before installing the router, plan the location and orientation relative to other devices and
equipment. For cooling purposes, allow a minimum of six inches of space between the sides, front,
and the back of the router and walls or other obstructions. If a router is installed within a perforated
enclosure, the perforations must cover at least 60 percent of the surface.
Brocade MLX Series and NetIron XMR Hardware Installation Guide
53-1003821-01
Crimping the power supply wire in the power lug
AWG power supply wire:
#8 AWG wire for 1200W power supply
#6 AWG wire for 1800W power supply
the power supply.
NOTE
DC return must be isolated from the router ground (DC-I) when connecting to the power supply.
"Attaching a management station"
"Activating the power source"
"Verifying proper operation"