5.5.2

Quick commissioning through the parameter menu

As an alternative to quick commissioning through the setup menu, commissioning using the
parameter menu provides the other solution for quick commissioning. This would be helpful
for those who are used to commissioning the inverter in this way.
Quick commissioning methods
● Conventional quick commissioning
This method requires you to complete quick commissioning with all the motor data given
in the parameter setting table below.
● Estimated quick commissioning
This method provides an easier way to complete quick commissioning with limited motor
data. Instead of entering all the motor data, you enter the rated motor power (P0301, in
kW) and then the inverter estimates and then sets the values of the rest of the motor data
including P0304, P0305, P0307, P0308, P0310 and P0311.
Restrictions on the estimated quick commissioning:
– This functionality is recommended at the rated supply voltage.
– This functionality is designed around the data for Siemens motors 1LE0001, 1TL0001,
– This functionality gives an estimate of the motor data values; however, if the motor is
– The value calculations only work with motors connected in star configuration and
– The calculations use the DC link voltage measurement and thus only work if mains is
– The calculations are accurate only for 4-pole motors.
– The 87 Hz characteristic is not supported.
Setting parameters
Note
In the table below, "●" indicates that you must enter the value of this parameter according to
the rating plate of the motor when you carry out the conventional quick commissioning.
SINAMICS V20 Inverter
Operating Instructions, 11/2016, A5E34559884-006
1LE1 and 1LA7 although it may make reasonable approximations for other motor
types.
to operatre near the limits of its capability (rated power and current), then you must
carry out the conventional quick commissioning.
assume the supply frequency is 50 Hz.
connected.
Commissioning via the built-in BOP
5.5 Quick commissioning
77

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents