9. Install the SCSI cables
Use 0.5 meter flexible SCSI cables to make connections between Bay A and Bay B of each storage
enclosure and between storage enclosures. Install the SCSI cables to conform to the system requirements
Refer to "Connecting SCSI Cabling" in the Chapter "Product Description" for more details about SCSI
cabling.
10. Complete the installation
a) Install filler panels to completely fill any unused space in the front and back of the rack (this is
important to maintain cooling).
b) Re-install the side panels (the rear rack door is not required for this installation; it should not be
installed and can be set aside).
c) Connect the PDUs to the power source. For redundant configurations, the PDU cables must be
connected to separate circuits or UPS for high availability power.
d) Bring the array enclosures on line and mount the file systems.
Appendix D. Back-to-Back Racking
Installation Procedure
249
Need help?
Do you have a question about the Surestore Disk Array 12h - And FC60 and is the answer not in the manual?