How to Programme
2.1.8 Initial Commissioning
The easiest way of carrying out the initial commissioning is by using the Quick Menu button and follow the quick set-up
2
2
procedure using LCP 102 (read table from left to right). The example applies to open loop applications:
Press
Par. 0-01 Language
Par. 1-20 Motor Power
[kW]
Par. 1-22 Motor Voltage
Par. 1-23 Motor Frequency
Par. 1-24 Motor Current
Par. 1-25 Motor Nominal
Speed
Par. 5-12 Terminal 27
Digital Input
Par. 1-29 Automatic Motor
Adaptation (AMA)
Par. 3-02 Minimum
Reference
Par. 3-03 Maximum
Reference
Par. 3-41 Ramp 1 Ramp up
Time
Par. 3-42 Ramp 1 Ramp
Down Time
Par. 3-13 Reference Site
18
FC 300 Programming Guide
Q2 Quick Menu
Set language
Set Motor nameplate power
Set Nameplate voltage
Set Nameplate frequency
Set Nameplate current
Set Nameplate speed in RPM
If terminal default is Coast
inverse it is possible to change
this setting to No function. No
connection to terminal 27 is
then needed for running AMA
Set desired AMA function.
Enable complete AMA is
recommended
Set the minimum speed of the
motor shaft
Set the maximum speed of the
motor shaft
Set the ramping up time with
reference to synchronous motor
speed, n
s
Set the ramping downdecel time
with reference to synchronous
motor speed, n
s
Set the site from where the
reference must work
®
MG.33.M9.02 - VLT