15 User Data Backup/Standard Commissioning
15.5 SINAMICS S120 standard commissioning with STARTER
15.5
SINAMICS S120 standard commissioning with STARTER
Requirements
Execution
15-466
A project must be available, created or loaded from a drive unit into the pro-
gramming device for the standard commissioning of SINAMICS S120. This
project is loaded as a reference project in the other drive units still to be com-
missioned.
The following conditions must be fulfilled:
S
The reference drive unit is fully configured.
S
You can create an online connection to all drive units.
S
The reference project is loaded into the STARTER.
Perform the following actions in the STARTER for each drive unit to be commis-
sioned.
1. Create a backup copy of the project: Project > Save As...
2. Access the drive unit online: Project > Connect to target system
3. Load the project into the drive unit: Target system > Load > Load to target
system
The drive unit applies the serial number from the previously located compo-
nents in the reference topology. This results in an inconsistency, which is
displayed in the project navigator.
4. Read the project back into the programming device: Target system > Load
> Load fully into the programming device (all p and r parameters)
5. Save your project: Project > Save
The configuration is now consistent, i.e., the same project states exist in the
target system and in the project.