8 Hindle Health System

8.3.2 Test Selection

After the initial introduction and safety screens, a screen prompts the
user to select the tests to run.
There are two (2) test selections. The second will not test alarms or
relays:
Operation, Set points, Alarms
Operation, Set points

8.3.3 Test Screens

The remaining screens are test screens. They prompt the user
through an interactive process to verify ATevo's operation. The
process will:
• Require the user to confirm that LED indicators are lit, that
relays change state, and that the set points are correct.
• Simulate alarm conditions and prompt the user to verify the
alarms operate and are confirmed by any connected SCADA
devices.
• Explain how to verify ATevo calibration and automatically enter
calibration mode if required.
After the Hindle Health System completes testing, ATevo will return
to the Home Screen. An event will be added to the log file along with
a time and date stamp. The results of each test are included in the
log file. The result status will indicate that each test PASSED, FAILED,
or was NOT RUN. The resulting log file can be used to prove NERC
compliance requirements for things such as verifying correct float
voltage.