Installing and Enabling Redundant Hardware
Installing Redundant Hardware
Enabling Redundant Hardware
Using the Web
Agent
Avaya P550R, P580, P880, and P882 Multiservice Switch User Guide, v5.3.1
The standard switch configuration does not include a redundant
controller or element. The correct process is to:
Install the redundant hardware
Enable the redundant hardware using either the Web Agent
or the CLI.
After the redundant hardware is enabled, the applicable redundant
component takes over if either a controller or any element fails.
To install redundant hardware:
1. Turn off all of the switch power supplies.
2. Replace the Primary switch controller with the new switch
controller. This ensures that the switch checks the status of
the new switch controller.
3. Insert the previously Primary switch controller into the
Redundant Controller Slot 1 (see Figure 7-1 for a P550/P580 or
Figure 7-2 for a P880/P882).
* Note: Controllers and elements are keyed to ensure that
a controller is not inserted into an element slot.
4. Install the redundant element into the redundant element slot 0
for the P550R/P580, (see Figure 7-1), or slot 6 for the P880/P882,
(see Figure 7-2).
5. Turn on the switch power supplies and log in.
6. Enable the Redundant Hardware as described in the next
section.
To enable redundant hardware using the Web Agent:
1. Select Switch Fabric from the System > Configuration
group on the Web Agent window. The Switch Fabric
Status dialog box opens. (Figure 7-3).
Configuring Redundancy Options
7-5