22. Close the drive wheel release valve (horizontal
operating position) (Fig. 336).
Fig. 336
23. Install the rear wheels. Torque the lug nuts to 90 - 95
ft-lbs. (122 - 129 Nm).
24. Remove the jack stands and lower the machine to
the ground.
Toro Z Master G3 3000/5000/6000 Series Service Manual
HYDRAULIC SYSTEM
UHT Transmission Replacement
(2012 & later models)
UHT Transmission Removal (2012 & later
models)
Note: The following procedures cover replacing
the left hand UHT transmission. The same
procedures can be followed to remove the
right hand UHT Transmission.
1. Position the machine on a level surface.
2. Disengage the PTO, move the motion control levers
to the neutral locked position. Apply the park brake.
3. Stop the engine, remove the key, and wait for all
PICT-8677a
moving parts to stop before leaving the operating
position.
4. Remove the negative battery cable from the battery.
5. Raise the rear of the unit and support it with two
jack stands under the right and left tie down loops.
Remove the RH and LH wheels from the unit (Fig.
337).
Fig. 337
DSCN-4311a
5
5-23