Nortel SONET AccessNode 800A Series Manual page 25

Outside plant cabinet installation
Table of Contents

Advertisement

Procedure 1-1 (continued)
Preparing the poured-in-place cabinet mounting pad
Action
Step
1
2
3
4
5
6
7
8
9
AccessNode Series 800A Outside Plant Cabinet Installation 323-3001-210 Issue 1.0
Action
Assemble the form as per the pad arrangement to be installed. Refer to
Figure 1-2 on page 1-10 through Figure 1-9 on page 1-17 for pad layouts.
Note: Make sure that all wood is cut to the exact dimensions. It is especially
critical that the 2x6s are ripped to the exact four-inch height so that the raised
portion of the anchor plate fits properly.
Place and level the form as required by the site plans.
Erect the anchor assembly as per the anchor kit to be installed.
Use Figure 1-10 on page 1-18 through Figure 1-13 on page 1-21 as you
assemble the anchor plate kit.
The assembly consists of:
galvanized steel plate, 11-gauge
anchoring bolts, 5/8-inch diameter (16 mm)
temporary angle supports
plastic caps to protect the bolt threads
Place the reinforcing welded wire mesh inside the form (see Figure 1-14 on
page 1-22).
Level the top of the form.
Place the anchor plate assembly on top of the form and secure it in place by
nailing the angles to the form.
Note: Use the plastic caps provided to protect the anchor bolt threads.
Position the cable ducts through the conduit template openings (see
Figure 1-1).
Note: Conduits should extend at least two inches (51 mm) above the anchor
assembly when possible, and should be plugged to prevent concrete from
entering the conduit.
Add bracing supports along the length of the form to keep it square against
the anchor plate and prevent bowing when the concrete is poured (see
Figure 1-14).
Note: Keep the conduit vertical while the concrete is poured.
Continue the pad installation by performing Procedure 1-2.
—continued—
Installing the pad 1-9

Advertisement