Nortel SONET AccessNode 800A Series Manual page 107

Outside plant cabinet installation
Table of Contents

Advertisement

Procedure 4-2 (continued)
Butting and stripping the VF, miscellaneous, T1 and maintenance cables
Step
10
11
12
13
AccessNode Series 800A Outside Plant Cabinet Installation 323-3001-210 Issue 1.0
Action
Remove all insulating gel throughout both of the cables with rags and De-gel.
Note: If using filled cable, remove as much of the gel as you can from the 600
pair cables. A cable that is completely degreased is easier to work with.
Cut two inches down at the 8-inch (20.32 cm) mark on the cable towards the
cable conduit parallel to the point where the grounding shield is folded.
Cut one inch to the left, across (perpendicular to) the cable. This creates the
bonding clamp mounting location on the cable.
Note: Later, a bond clamp is attached to this door or flap in order to ground
both of the cables.
Repeat this procedure for each OSP cable (except the fiber cable) pulled into
the cabinet in Procedure 4-1 on page 4-4.
—end—
Installing the OSP cables 4-11

Advertisement