Procedure; Preparing The Cabinet For Installation - Nortel SONET AccessNode 800A Series Manual

Outside plant cabinet installation
Table of Contents

Advertisement

2-14 Installing the cabinet

Procedure 2-3

Preparing the cabinet for installation

Use this procedure to connect the lifting crane to the S800A cabinet and to
prepare the cabinet for installation.
Lifting and moving the cabinet
Before lifting and moving the cabinet, remove any debris from the pad. Verify
that the pad is level and free from obstructions.
Observe the following warnings and cautions when lifting and moving the
cabinets:
AccessNode 323-3001-210 Issue 1.0
DANGER
Safety hazard and cabinet lifting failure
Do not lift the cabinet without following proper lifting
procedures.
Failure to comply with this warning can cause serious or fatal
bodily injury and damage to the cabinet.
CAUTION
Potential equipment damage and personal injury
Barricade the lift area. Do not allow cars to be parked within
twenty-five feet of the lift radius. All persons within the
barricaded area should wear a hard hat and steel-toed safety
shoes. Do not physically assist the rigging crew. Only the
crane rigging crew performs crane setup and rigging
procedures.
CAUTION
Possible equipment damage
Do not lift cabinet with batteries installed.
CAUTION
Possible equipment damage
Align the hoist line over the center of gravity of the load to
eliminate load swinging. Do not exceed the lifting capacity
of the crane.