10-6 Adjusting the rectifier and the dc distribution shelf
Procedure 10-1 (continued)
Powering the rectifier(s)
Step
3
Table 10-2
AC option power-up steps
If the ac option
installed is the
Load center
AC pedestal
4
AccessNode 323-3001-210 Issue 1.0
Action
Perform the following steps as per the type of ac option installed on the
cabinet:
Then perform the following steps
• Set the main circuit breaker (MAIN) to the ON position
(see Figure 10-2 on page 10-7).
• Go to step 4.
• Set the transfer knife switch to either:
– the normal (NORMAL AC POWER) position
or, if an external emergency power generator is being used,
– the emergency power (GENERATOR POWER) position
(see Figure 10-3 on page 10-8).
• Set the MAIN transfer circuit breaker to the ON position in
the load center (see Figure 10-2 on page 10-7).
• Go to step 4.
Switch EQL switch on the dc distribution shelf to the OFF position.
—continued—