7-10 Routing and splicing the fiber cable
Procedure 7-1 (continued)
Routing the OSP fiber cable directly to the FPP
Step
5
6
Figure 7-4
Routing of fiber cable to fiber distribution/patch panel rear view
Cabinet rear (swing frames removed)
AccessNode 323-3001-210 Issue 1.0
Action
Loop the fiber down the inside wall of the AC compartment on the rear side
of the baffle to the bottom of the wall.
Route the fiber across the top of the batteries and up the inside wall of the
termination compartment (see Figure 7-4).
—continued—
FW-15129
Upper entrance slot
Use cable-ties above
the thermostat
approximately as shown
Interior air baffle
Service loop no lower
than the bottom of the
swing frames
FW-15129