Outside plant cabinet installation
Table of Contents

Advertisement

Procedure 7-3 (continued)
Routing the OSP fibers in split flex tubing to the FPP
Step
9
10
11
12
13
14
Figure 7-13
Patch cord routing on the interior AC compartment wall
DSX
RPTR
Battery breaker
panel
Rear
DC distribution
shelf
Rectifier
shelf
Left rear equipment
swing frame open
AccessNode Series 800A Outside Plant Cabinet Installation 323-3001-210 Issue 1.0
Action
Dress the tubing back toward the right side of the swing frame.
Tie wrap the tubing in place as shown in Figure 7-11 on page 7-25.
Route the tubing to the inside wall of the AC compartment (see Figure 7-13).
Note: Leave a sufficient service loop in the routing to accommodate the swing
fame opening and closing without putting undue pressure or tension on the
tubing.
Tie wrap the tubing to the cable tie strips on the inside wall of the AC
compartment as shown in Figure 7-13.
Route the tubing around to the rear side of the air baffle to the cable tie strips
above the thermostat.
Tie wrap the tubing to the cable hooks in the roof as shown in Figure 7-13.
Inside view facing AC compartment
—continued—
Routing and splicing the fiber cable 7-27
FW-15137
Front
ABM
CDS shelf
CDS shelf
Right front equipment
swing frame open
FW-15137
Route the spiral wrap
tubing against
the tie-down strip when
routing to the ABM.
Form the service loop
before entering the swing
frame cabling cutout