Nortel SONET AccessNode 800A Series Manual page 163

Outside plant cabinet installation
Table of Contents

Advertisement

Procedure 6-8 (continued)
Connecting the outside plant cable pairs to 710 or 3M MS2 DPM connectors without
cross-connect
Action
Step
1
2
3
Figure 6-17
Tie wrap binder groups to the ladder supports
Tie wrap binder groups
up the ladder supports
AccessNode Series 800A Outside Plant Cabinet Installation 323-3001-210 Issue 1.0
Action
From the base of the OSP cables, tie wrap each bundle against the left rear
wall ladder position (see Figure 6-17).
Position the binder groups from the OSP cables in the proper sequence and
secure them against the ladder supports.
Run each bundle in its proper pair count order from top to bottom, following
standard color code assignments.
—continued—
Routing and terminating the VF cables 6-37