Table 5. 1xxxyyyy SRCs (continued)
v Follow the suggested actions in the order in which they are listed in the Action column until the problem is
solved. If an action solves the problem, then you can stop performing the remaining actions.
v See Chapter 3, "Parts listing, Type 7998," on page 235 to determine which components are CRUs and which
components are FRUs.
1xxxyyyy
Description
Error Codes
2672
Blades PEU3 voltage alert
3134
I2C problem found with the
PEU3 hardware monitoring
chip
8400
Invalid configuration decode
8402
Unable to get VPD from the
concentrator
8413
Invalid processor 1 VPD
8414
Invalid processor 2 VPD
Action
Perform the DTRCARD Symbolic CRU isolation procedure by
completing the following steps:
1. Reseat the PCIe expansion card.
2. If the problem persists, replace the expansion card.
3. If the problem persists, go to "Checkout procedure" on page
186.
4. If the problem persists, replace the system board and chassis
assembly, as described in "Replacing the Tier 2 system-board
and chassis assembly" on page 274.
The DTRCARD Symbolic CRU isolation procedure is in "Service
processor problems" on page 205.
Perform the DTRCARD Symbolic CRU isolation procedure by
completing the following steps:
1. Reseat the PCIe expansion card.
2. If the problem persists, replace the expansion card.
3. If the problem persists, go to "Checkout procedure" on page
186.
4. If the problem persists, replace the system board and chassis
assembly, as described in "Replacing the Tier 2 system-board
and chassis assembly" on page 274.
The DTRCARD Symbolic CRU isolation procedure is in "Service
processor problems" on page 205.
1. Check for server firmware updates.
2. Apply any available updates.
3. If the problem persists:
a. Go to "Checkout procedure" on page 186.
b. Replace the system-board and chassis assembly, as described
in "Replacing the Tier 2 system-board and chassis assembly"
on page 274.
1. Go to "Checkout procedure" on page 186.
2. Replace the system-board and chassis assembly, as described in
"Replacing the Tier 2 system-board and chassis assembly" on
page 274.
1. Go to "Checkout procedure" on page 186.
2. Replace the system-board and chassis assembly, as described in
"Replacing the Tier 2 system-board and chassis assembly" on
page 274.
1. Go to "Checkout procedure" on page 186.
2. Replace the system-board and chassis assembly, as described in
"Replacing the Tier 2 system-board and chassis assembly" on
page 274.