5.4
L

Switch on controller

Step
1. Assign X5/28 to LOW level (CINH).
2. Connect the travel range limit switch to terminals X5/E1 and X5/E2 See:
3. Assign digital input signals to (X5/E3 ... X5/E5).
4. Switch on mains voltage.
5. Adapt DC-bus voltage threshold with C0173 to the mains voltage.
6. Check whether the drive is ready for operation.
7. For operation with a fieldbus module, additional settings are
necessary.
Tip!
For applications with active loads (e. g. hoists) the code C0172* must be set to C0172 = 0 [Volt] to
generate an overvoltage message (OU).
As long as the overvoltage message is applied
pulse inhibit is set and
the drive has no torque.
The controller inhibit is evaluated, among other things, by the "holding brake (BRK)" (see chapter in
the corresponding 9300 System Manual).
*) C0172 = "OV reduce - Threshold for activating the brake torque reduction before OU message"
Commissioning
4-24
Assign X5/E1 and X5/E2 with HIGH level if you do not use any travel
range limit switches.
The controller is ready for operation after approx. 2 s.
When the green LED is flashing:
– Controller is ready for operation
When green LED is off and red LED is flashing:
– A fault has occurred. Eliminate the fault before proceeding with
commissioning. See chapter 8 "Troubleshooting and fault
elimination".
See Operating Instructions for the corresponding fieldbus module.