1. Confirm that the DBS 824 power switch is OFF.
2. Plug the power cord into a dedicated 120V 15 amp AC wall outlet.
Note: A surge protector should be installed on the power cord.
3. Set SW1 on the CPC card to RAM CLEAR.
Figure .W?. CPC
memory clear switch
""'I
Status LED
II I I
Battery
IIIII
III
I
CAUTION:
Some early CPC cards
have RAM'HOLD and
RAM CLEAR reversed
/ ) 1.
Check the silk screen
Power
Switch
CAUTION:
Setting SW 1 to
RAM CLEAR Erases
Programming
Power Supply
I
4. Turn the power switch on.
As the system loads, the Status LED lamp on the CPC card flashes.
5. Once the Status LED lamp on the CPC card stops flashing, set SW1 on
the CPC to HOLD.