Chapter 5

Checking the installation prerequisites

Refer to the following sections for information on BCM system installation prerequisites:

"General requirements"

"Environmental requirements"

"Electrical requirements"
"Site telephony wiring requirements" on page 88
"System equipment, supplies, and tools" on page 89
General requirements
Before you install the BCM main unit or expansion unit, complete the following actions:
Determine the location for the BCM main unit (or expansion unit), telephones, and other
equipment based on spacing and electrical requirements.
Order the required trunks from the central office.
Ensure that you have all the equipment and supplies you need to install the system.
Environmental requirements
Ensure you meet the installation environmental requirements. The installation area must be:
a minimum of 4 m (13 ft.) from equipment such as photocopiers, electrical motors, and other
equipment that produces electromagnetic, radio frequency, and electrostatic interference
within 1.5 m (5 ft.) of a three-wire grounded electrical outlet
clean, free of traffic and excess dust, dry, and well ventilated
within the temperature ranges of 10°C and 40°C (50°F and 104°F)
between 20% and 80% non-condensing relative humidity
structurally strong enough and with enough space to support the BCM units
a minimum of 46 cm (18 in.) from the floor
Note: The installation area must be of sufficient height from the floor to prevent water
damage.
Chapter 5 Checking the installation prerequisites
BCM200/400 4.0 Installation and Maintenance Guide
87