High-level overview of the installation process

You complete the installation process in stages. You can complete some stages in parallel.
Other stages require certain tasks first. The order in which you complete the stages depends on
the suggested order, local practice, and the personnel available. The high-level stages are:
Installing the G650 media gateways.

Cabling the media gateways.

Connecting to the customer network which includes media servers, C-LAN, VAL, and so
forth.
Installing and wiring telephones and trunks.
Completing the installation administration which includes clear alarms, enable alarm
reporting, backup translation, and so forth.
Testing the complete configuration.
These high-level stages are described below.

Installing the media gateways

You can complete this stage in parallel with installing and configuring the server complex. You
must install and turn on the media gateways before you complete many of the other stages.
Cabling the media gateways
In this stage, you attach the cables of the media gateways to the main distribution frame and the
patch panels. This stage usually comes after you install the media gateways and before you
install traditional telephones.

Connecting the media gateways

In this stage, you connect the media gateways to the server complex through Ethernet cables.
You also program the IP Server Interface (IPSI) circuit packs during this stage. Before you can
complete this stage, the G650 Media Gateway must be installed and the server complex must
be operational.