FINAL DRIVE
FRONT DRIVE SHAFT INSTALLATION
1. Install new spring ring
anti-seize compound to the splines
2. Align splines of drive shaft with front gearcase and
reinstall the drive shaft. Use a rubber mallet to tap on
the outboard end of the drive shaft if necessary
3. Install drive shaft into the front bearing carrier.
4. Install the upper and lower ball joint ends into the
front bearing carrier.
7.12
q
on drive shaft. Apply an
w
.
5. Install new pinch bolts and nuts
specification.
TORQUE
Ball Joint Fasteners:
42 ft-lbs (57 Nm)
6. Apply Anti-Seize to drive shaft axle splines.
7. Install front wheel hub assembly
and hand tighten the castle nut. Install washers with
domed side out.