Slowly push the switch contact
10.
in the direction of flow, until the
contact opens. This switch point
should be set as accurately as
possible because it affects the
accuracy of the switch point
adjustment scale values (if
needed, repeat steps 9 and 10).
Retighten the set screws
11.
(Fig. 73/1) observing the proper
tightening torque of the screws
(
Ä
Chapter 11.1 "Tightening
torque of screws" on page 85)
Apply the enclosed switch con-
12.
tact data plate to the side of the
switch contact so that the refer-
ence arrow is in alignment with
the lowest scale mark. If a refer-
ence tick mark is on the data
plate (recognizable as a thinner
line), it is to be used as the
alignment mark. The adhesive
surface must be dry and free of
oil and grease.
13.
Adjust the desired flow rate (cut-
off point) on the switch point
adjustment scale.
Attach the female socket and
14.
gasket and tighten the fixing
screw.
23.02.2015

Measures to be taken after maintenance work

8.6 Measures to be
taken after mainte-
nance work
Take the following steps after comple-
tion of maintenance work and before
switching on the device:
Check all previously loosened/
1.
released screw connections for
tightness.
Ä
Chapter 11.1 "Tightening
torque of screws" on page 85
Clean the work area and remove
2.
all residual materials, packaging,
substances or spills.
Maintenance